Shepherd and Wedderburn LLP
October 25, 2021 - Scotland
Liquidated Damages and Partial Possession
The Technology and Construction Court (TCC) in Eco World - Ballymore Embassy Gardens Company Ltd v Dobler UK Ltd [2021] EWHC 2207 (TCC) enforced a liquidated damages (LDs) clause that did not allow for a proportionate reduction following partial possession of sections of a development. The TCC rejected that the clause was a penalty, and considered the argument that an invalid liquidated damages clause could still operate as a valid cap of liability.
BackgroundEco World (Eco) employed Dobler (UK) Ltd (Dobler) to design, supply and install façade and glazing works at Nine Elms, London (the Contract). The Contract was based on the JCT 2011 Construction Management Trade Contract (with amendments). Dobler was engaged on three “blocks” of the residential development (Blocks A, B and C), together referred to as Building A04. The revised completion date was 30 April 2018. There was no sectional completion in the Contract, but there was a provision regarding take-over or possession prior to Practical Completion (PC). During the week ending 15 June 2018, Eco took over Blocks B and C, but Block A was outstanding. Eco took over the remainder of the works on 20 December 2018, and PC was certified. Following PC, a dispute arose as to the level of applicable LDs LDs mechanismThe Contract provided for LDs in the event of Dobler’s delay (clause 2.32.1). It allowed an initial grace period of four weeks, and thereafter a weekly sum with a cap: “Liquidated damages will apply thereafter at the rate of £25,000 per week (or pro rata for part of a week) up to an aggregate maximum of 7% of the final Trade Contract Sum…” The relevant contractual notice to be issued for LDs to be levied was to specify whether LDs were to be paid at the contract rate, or a “lesser rate stated in the notice”. Technology and Construction Court (TCC) actionThree adjudications took place between the parties. These included arguments over extension of time, valuation and LDs. Following the third adjudication, Eco commenced Part 8 proceedings in the TCC to determine the following questions:
Parties' positionsEco argued:
Dobler argued:
DecisionThe TCC held:
Alternative argument re capAlthough not necessary given the finding above, the TCC also considered Dobler’s alternative argument that even if the LDs mechanism was void and/or inoperable, the ‘cap’ in the clause would still apply to any general or unliquidated damages. An important factor to consider in this context would be whether the cap was intended to provide a limitation of liability for any delay costs. In considering the Contract as a whole, the TCC determined that the 7% cap in this case “would operate as a limitation of liability provision, even if the liquidated damages were void or a penalty”. Therefore, even if Eco had been successful in arguing the LDs clause was void and/or unenforceable, its general damages claim would still have been subject to the 7% cap. Points to take awayThe lessons to learn from this case are:
For more information, please contact Iain Drummond, Partner in our property and infrastructure team, at iain.drummond@shepwedd.com. |