Shepherd and Wedderburn LLP
October 19, 2021 - Scotland
TCC decides multiple payment applications can be one dispute
The Technology and Construction Court (TCC) in Quadro Services Ltd v Creagh Concrete Products Ltd [2021] EWHC 2637 (TCC) held that a claim referred to adjudication with three separate payment applications was still considered a single dispute for the purposes of adjudication. The adjudicator therefore did have jurisdiction to consider all three payment applications to determine the sum due, and the adjudicator’s decision was enforced.
Background to the Quadro v Creagh disputeThe parties entered into an oral agreement for the provision of labour to Creagh Concrete. It was agreed that the contract was a construction contract for the purposes of the Housing Grants, Construction and Regeneration Act 1996. The contract did not contain any adjudication provisions, and therefore the Scheme for Construction Contracts (England and Wales) Regulations 1998 (as amended) applied. The works were carried out by Quadro and they made applications for payment and raised invoices. Creagh did not pay three invoices. Two of the invoices had been ‘approved’ by Creagh, with Creagh confirming an invoice could be raised in line with the relevant payment application. Creagh failed to respond to the third payment application, or issue a payment notice or pay less notice in response. Given this failure, Quadro proceeded to issue an invoice in line with its payment application. AdjudicationQuadro issued adjudication proceedings in relation to the three outstanding invoices. Quadro’s position in adjudication was that there was no defence to its claim for payment for all three invoices, given Creagh’s acceptance of the first two payment applications, and Creagh’s failure to respond to the third payment application. Creagh raised a jurisdictional challenge in the adjudication, arguing that the matter referred to adjudication contained three disputes, as opposed to one. The general position is that only one dispute can be referred to adjudication, unless both parties agree otherwise. Quadro argued that only one dispute had been referred, as to what were the outstanding sums owed to Quadro by Creagh under one contract; it classified the three invoices as “sub issues”. The Adjudicator agreed with Quadro that the dispute referred was only one dispute, and issued his decision. He awarded Quadro its full claim, together with interest and compensation under the Late Payment of Commercial Debts (Interest) Act 1998. Creagh failed to pay. TCC enforcement actionQuadro raised adjudication enforcement proceedings given Creagh’s failure to pay. Creagh resisted enforcement on the basis that the adjudication covered multiple disputes. Creagh presented four reasons to support its argument:
The TCC held:
The TCC therefore enforced the Adjudicator’s decision. Points to take awayThe practical points to take away from this case for parties adjudicating are:
It is also of interest that the TCC commented on the policy behind the adjudication process; this shows again the courts’ support for the Adjudication process. The decision further demonstrates that the courts will look to enforce an Adjudicator’s Decision, unless there is a very good reason not to. For more information, please contact Iain Drummond, Partner in our property and infrastructure team, at iain.drummond@shepwedd.com. |